Written Question · S3W-36737 · Session 3

Further to the answer to question S3W-36525 by Alex Neil on 4 October 2010, whether it has investigated the reason for the average time fro…

Answered Asked by Tavish Scott LD Lodged 6 Oct 2010

The question

To ask the Scottish Executive, further to the answer to question S3W-36525 by Alex Neil on 4 October 2010, whether it has investigated the reason for the average time from referral to Stage Four of the installation of Energy Assistance Package measures in Shetland being 123% higher than the national average and 58% higher than the local authority with the next highest average.

The answer

Answered by Alex Neil on 28 Oct 2010 · 22 days after it was lodged, on time

Officials regularly monitor delivery times and discuss issues with the managing agent.
Reasons for the higher average delivery time in Shetland for the 10 installations to the end of August 2010, include electrical load checks or load upgrades by a third party supplier, which adds on average 38 days to every installation. Connections to the district heating system by a third party are similarly affected, adding on average 28 days.

In the Official Report