Written Question · S3W-35939 · Session 3
What the cost has been to Scottish Natural Heritage of implementing control orders on estates under section 7 of the Deer (Scotland) Act 19…
The question
To ask the Scottish Executive what the cost has been to Scottish Natural Heritage of implementing control orders on estates under section 7 of the Deer (Scotland) Act 1996 in each of the last five years.
The answer
The costs of implementing control agreements made under Section 7 of The Deer Scotland Act 1996, including a profiled estimate for 2010, are set out in the following table:
>
| Habitat Assessment Costs (£)
| Deer Census (£)
| DCS staff costs
| Total (£)
2006
| 18,000
| 33,000
| 104,459
| 155,459
2007
| 71,030
| 35,800
| 104,459
| 211,289
2008
| 126,725
| 78,944
| 104,459
| 310,128
2009
| 74,000
| 76,000
| 104,459
| 254,459
2010
| 25,500
| 76,000
| 104,459
| 205,959
In addition, £160,000 of assistance was provided under section 12 of the Deer (Scotland) Act 1996 over two culling seasons in 2005-06 and 2006-07 in support of a Section 7 control agreement. These figures do not include the cost of any emergency measures taken under section 10 of the act.
>
| Habitat Assessment Costs (£)
| Deer Census (£)
| DCS staff costs
| Total (£)
2006
| 18,000
| 33,000
| 104,459
| 155,459
2007
| 71,030
| 35,800
| 104,459
| 211,289
2008
| 126,725
| 78,944
| 104,459
| 310,128
2009
| 74,000
| 76,000
| 104,459
| 254,459
2010
| 25,500
| 76,000
| 104,459
| 205,959
In addition, £160,000 of assistance was provided under section 12 of the Deer (Scotland) Act 1996 over two culling seasons in 2005-06 and 2006-07 in support of a Section 7 control agreement. These figures do not include the cost of any emergency measures taken under section 10 of the act.
In the Official Report
No contribution in the Official Report cites S3W-35939 by reference.