The question
To ask the Scottish Executive, further to the answer to question S3W-35084 by Stewart Stevenson on 26 July 2010, what savings would be made if the final tranche of compulsory purchase orders for the Borders railway project were abandoned.
The answer
It is estimated that if the final tranche of compulsory purchase orders in relation to land/access rights required to maintain the Borders Railway were not served, savings would be in the region of £170,000
- £200,000.
- £200,000.
In the Official Report