How much has been spent on consultants on the Borders railway project broken down by firm.
The question
To ask the Scottish Executive how much has been spent on consultants on the Borders railway project broken down by firm.
The answer
As of June 2010, consultant costs for the Borders railway project were approximately £2.7 million with a breakdown of costs as follows:
Consultancy
| £
Dundas and Wilson
| 548,638
Environmental
| 457,594
Turner and Townsend
| 59,577
Ernst and Young
| 1,344,932
Partnerships UK
| 145,278
Mott MacDonald
| 14,981
Weber Shandwick
| 206,041
Total
| 2,777,041
Consultancy
| £
Dundas and Wilson
| 548,638
Environmental
| 457,594
Turner and Townsend
| 59,577
Ernst and Young
| 1,344,932
Partnerships UK
| 145,278
Mott MacDonald
| 14,981
Weber Shandwick
| 206,041
Total
| 2,777,041