Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S3W-34901 · Session 3

What the benefit-cost ratio of the Glasgow Airport Rail Link project was when it was cancelled.

Answered Asked by Charlie Gordon Lab Lodged 25 Jun 2010

The question

To ask the Scottish Executive what the benefit-cost ratio of the Glasgow Airport Rail Link project was when it was cancelled.

The answer

Answered by Stewart Stevenson on 30 Jun 2010 · 5 days after it was lodged, on time

When the project was cancelled in September 2009 it had a benefit to cost ratio (BCR) of 1.1.

In the Official Report

No contribution in the Official Report cites S3W-34901 by reference.