Further to the answer to question S3W-31800 by Nicola Sturgeon on 10 March 2010, what it means by near future and whether it considers that…
The question
To ask the Scottish Executive, further to the answer to question S3W-31800 by Nicola Sturgeon on 10 March 2010, what it means by near future and whether it considers that there has been an unacceptable delay in the publication of the findings of the Technical Advisory Group on Resource Allocation (TAGRA).
The answer
I refer the member to the answer to question S3W-33780 on 1 June 2010, which provides an update of the work of Technical Advisory Group on Resource Allocation (TAGRA) relating to its remote and rural review. All answers to written parliamentary questions can be found on the Parliament''s website, the search facility for which can be found at:
www.scottish.parliament.uk/Apps2/Business/PQA/Default.aspx.
The Scottish Government does not consider there to have been an unacceptable delay in the publishing of TAGRA''s findings. TAGRA has not yet completed its report, and its findings will be published once it has done so. The evidence that has been viewed by TAGRA as part of its research is published on its website at http://www.tagra.scot.nhs.uk/meetingpapers.html, alongside the minutes from its meetings, as part of its commitment to having a fair and transparent formula.
www.scottish.parliament.uk/Apps2/Business/PQA/Default.aspx.
The Scottish Government does not consider there to have been an unacceptable delay in the publishing of TAGRA''s findings. TAGRA has not yet completed its report, and its findings will be published once it has done so. The evidence that has been viewed by TAGRA as part of its research is published on its website at http://www.tagra.scot.nhs.uk/meetingpapers.html, alongside the minutes from its meetings, as part of its commitment to having a fair and transparent formula.
In the Official Report
No contribution in the Official Report cites S3W-34137 by reference.