In what ways the WATERS fund will differ from the Wave and Tidal Energy Support Scheme in terms of (a) project eligibility, (b) applicant e…
The question
To ask the Scottish Executive in what ways the WATERS fund will differ from the Wave and Tidal Energy Support Scheme in terms of (a) project eligibility, (b) applicant eligibility, (c) the type of support available, (d) the distribution of payments and (e) the expected number of successful applicants.
The answer
The eligibility criteria under WATERS are broadly similar to those which applied under WATES. The key difference with respect to projects is that there is no requirement to locate at EMEC, or to connect directly to the relevant local distribution network. Meanwhile, WATERS has also ruled out from its current call applications for collaborative projects, as these have the option to respond to a separate call from the Technology Strategy Board.
While capital intervention under WATES was capped at 40%, WATERS will be able to award grants ranging from 25% to 50% of eligible costs, depending on both the nature of the application and the size of the applicant. Unlike WATES, there will be no revenue payments available through the WATERS fund.
Payments under WATERS will be made quarterly in arrears, based upon actual expenditure against pre-defined eligible costs. This is similar to the system of payments under WATES, which have been issued in arrears subject to the achievement of key agreed milestones. The expectation is that projects receiving support through WATERS will typically be of 18 to 24 month duration.
One area where WATES and WATERS are entirely in sync is that neither fund opened with a view on the expected number of successful applicants.
While capital intervention under WATES was capped at 40%, WATERS will be able to award grants ranging from 25% to 50% of eligible costs, depending on both the nature of the application and the size of the applicant. Unlike WATES, there will be no revenue payments available through the WATERS fund.
Payments under WATERS will be made quarterly in arrears, based upon actual expenditure against pre-defined eligible costs. This is similar to the system of payments under WATES, which have been issued in arrears subject to the achievement of key agreed milestones. The expectation is that projects receiving support through WATERS will typically be of 18 to 24 month duration.
One area where WATES and WATERS are entirely in sync is that neither fund opened with a view on the expected number of successful applicants.
In the Official Report