Whether NHS Greater Glasgow and Clyde is reviewing its capital programme for 2010-11 and beyond and whether this includes the rebuilding of…
The question
To ask the Scottish Executive whether NHS Greater Glasgow and Clyde is reviewing its capital programme for 2010-11 and beyond and whether this includes the rebuilding of the Southern General Hospital.
The answer
All NHS boards keep their activity under review in order to ensure the delivery of best value for taxpayers'' investment.
NHS Greater Glasgow and Clyde is currently reviewing its capital programme and expects to conclude this review by 15 May 2010 when a capital plan for 2010-11 and beyond will be presented to the NHS board''s performance review group for approval.
However, this does not affect the delivery of the new South Glasgow Hospital.
NHS Scotland and NHS Greater Glasgow and Clyde remain totally committed to the delivery and construction of the New South Glasgow Hospital project, which will be operational in 2015.
NHS Greater Glasgow and Clyde is currently reviewing its capital programme and expects to conclude this review by 15 May 2010 when a capital plan for 2010-11 and beyond will be presented to the NHS board''s performance review group for approval.
However, this does not affect the delivery of the new South Glasgow Hospital.
NHS Scotland and NHS Greater Glasgow and Clyde remain totally committed to the delivery and construction of the New South Glasgow Hospital project, which will be operational in 2015.
In the Official Report