Further to the answer to question S3W-18527 by Stewart Stevenson on 17 December 2008, when it will announce a timetable for the constructio…

Answered Asked by Richard Baker Lab Lodged 17 Mar 2010

The question

To ask the Scottish Executive, further to the answer to question S3W-18527 by Stewart Stevenson on 17 December 2008, when it will announce a timetable for the construction of improvements at the Haudagain roundabout in Aberdeen.

The answer

Answered by Stewart Stevenson on 16 Apr 2010 · 30 days after it was lodged, on time

We have previously made clear that work on Haudagain Roundabout will be completed before financial responsibility transfers to the Council.

In the Official Report

No contribution in the Official Report cites S3W-32471 by reference.