To ask the Scottish Executive what projects have not yet received all of the funding allocated under the Wave and Tidal Energy Support Scheme.

The answer

Answered by Jim Mather on 2 Mar 2010 · 29 days after it was lodged, 1 day after it was due

The following projects have not drawn down their total funding allocated under the Wave and Tidal Energy Support Scheme (WATES):
ScottishPower Renewables (previously known as CRE Energy)
Ocean Power Technology
Scotrenewables Marine Power Ltd.
The Scottish Government is working closely with these developers and remain confident that these projects will meet the WATES deadline of March 2011.
Unfortunately, following discussions with AWS Ocean Energy Ltd, the Scottish Government has had to withdraw that company''s WATES award of £1.76 million. This is because the thorough review undertaken by AWS, and the significant changes aimed at improving their technology which emerged from that process, meant that their revised project and development plans no longer met the original WATES eligibility criteria.
AWS has since achieved welcome success in securing a £2 million investment from Scottish Enterprise''s Scottish Co-investment Fund and further private investment from the Shell Technology Ventures Fund.
The Scottish Government will recycle the £1.76 million into a new wave and tidal fund, which we expect to launch during March.