Further to the answers to questions S3W-17457 and S3W-26834 by Jim Mather on 14 November 2008 and 8 September 2009 respectively, what proje…

Answered Asked by Lewis Macdonald Lab Lodged 1 Feb 2010

The question

To ask the Scottish Executive, further to the answers to questions S3W-17457 and S3W-26834 by Jim Mather on 14 November 2008 and 8 September 2009 respectively, what projects have received grants under the Wave and Tidal Energy Support Scheme to date; how much each project has received, and on what date each funding allocation was made.

The answer

Answered by Jim Mather on 2 Mar 2010 · 29 days after it was lodged, 1 day after it was due

Six projects have received grant payments to date totalling £2,196,080. These are as follows:
Name of Developer
| Actual Milestone
Payment
| Financial Year
Payment Made
| Date
Paid

Ocean Power Technology
| £46,295
| 2007-08
| May 2008

Ocean Power Technology
| £73,336
| 2007-08
| May 2008

Ocean Power Technology
| £64,597
| 2007-08
| August 2007

Ocean Power Technology
| £88,718
| 2009-10
| May 2009

Total
| =SUM(ABOVE) \# "£#,##0.00;(£#,##0.00)" £272,946
|
|


Name of Developer
| Actual Milestone
Payment
| Financial Year
Payment Made
| Date
Paid

Open Hydro
| £182,987
| 2007-08
| March 2008

Open Hydro
| £602,305
| 2007-08
| December 2007

Open Hydro
| £54,526
| 2007-08
| July 2007

Open Hydro
| £284,785
| 2008-09
| April 2009

Total
|