Written Question · S3W-31252 · Session 3
What progress has been made with the pilot for the schools investment programme referred to in the Scottish Future’s Trust corporate plan.
The question
To ask the Scottish Executive what progress has been made with the pilot for the schools investment programme referred to in the Scottish Future’s Trust corporate plan.
The answer
The pilot programme referred to in the Scottish Futures Trust''s corporate plan is underway involving a joint procurement project with Lasswade High School in Midlothian and Eastwood High School in East Renfrewshire. The OJEU notice for the design team appointment was issued in November 2009. The short listed design teams have been advised and procurement is progressing.
In the Official Report
No contribution in the Official Report cites S3W-31252 by reference.