When funding will come on stream to fund (a) secondary and (b) primary schools through the schools investment programme.

Answered Asked by Andy Kerr Lab Lodged 29 Jan 2010

The question

To ask the Scottish Executive when funding will come on stream to fund (a) secondary and (b) primary schools through the schools investment programme.

The answer

Answered by Keith Brown on 11 Feb 2010 · 13 days after it was lodged, on time

As the then Cabinet Secretary for Education and Lifelong Learning said during her statement to Parliament about the new £1.25 billion school building programme on 17 June 2009, funding will start from 2010-11 and continue to 2017-18. We expect the first schools to be completed will be primary schools in 2011 and the first secondary schools will be completed in 2013.

In the Official Report

No contribution in the Official Report cites S3W-31249 by reference.