Written Question · S3W-31245 · Session 3
When it expects the first school to be completed under the Scottish Futures Trust school investment programme.
The question
To ask the Scottish Executive when it expects the first school to be completed under the Scottish Futures Trust school investment programme.
The answer
As the then Cabinet Secretary for Education and Lifelong Learning said during her statement to Parliament about the new £1.25 billion school building programme on 17 June 2009, we expect the first primary school to be completed in 2011.
In the Official Report
No contribution in the Official Report cites S3W-31245 by reference.