The question

To ask the Scottish Executive how the (a) estimated capital value and (b) timescale of the Scottish Crime Campus at Gartcosh compares with the original project cost and timescale estimates.

The answer

Answered by Kenny MacAskill on 9 Feb 2010 · 11 days after it was lodged, on time

The project was launched in January 2007 with an estimated cost of £65 million and a target date for completion of late 2010. The project has increased in size and scope and, subject to contract, the current estimated cost is £82 million and full occupation is planned for mid 2013.

In the Official Report

No contribution in the Official Report cites S3W-31238 by reference.