Written Question · S3W-31237 · Session 3

How the (a) estimated capital value and (b) timescale of the Glasgow Airport Rail Link compares with the original project cost and timescal…

Answered Asked by Andy Kerr Lab Lodged 29 Jan 2010

The question

To ask the Scottish Executive how the (a) estimated capital value and (b) timescale of the Glasgow Airport Rail Link compares with the original project cost and timescale estimates.

The answer

Answered by Stewart Stevenson on 5 Feb 2010 · 7 days after it was lodged, on time

The original cost and timescale of the Glasgow Airport Rail Link (GARL) project are set out in the following table:
Glasgow Airport Rail Link (GARL) Cost (All Figures in £ Million) and Schedule
Date
| Out turn Cost Range
| Anticipated Final Cost
| Timeframe for Delivery

March 2006
| 170 “ 210
| 187.5
| Q1/2010


As the Paisley Corridor re-signalling (PCR) project would have led to significant closures of GARL, the decision was taken to merge the projects and align the timescales. Following the combination of the GARL project with the PCR renewal project, (GARL/PCR), the last estimate of the combined project, at the point where the branch line element was cancelled, are set out in the following table:
Glasgow Airport Rail Link/Paisley Corridor Renewal (GARL/PCR) Cost (All Figures in £ Million) and Schedule
Date
| Out turn Cost Range
| Anticipated Final Cost
| Timeframe for Delivery

September 2009
| 386 “ 408
| 397.5
| Q3/2013


March 2006 was the first time that the project cost had been expressed in out turn figures previously having been expressed in Q4/2004 prices (£160 million Q4/2004 equating to £170 million to £210 million Q1/2010 out turn). The out turn cost includes an assessment of the likely impact of cost indexation within the rail / construction industry over the lifecycle of the projects delivery.