How the (a) estimated capital value and (b) timescale of the Southern General Hospital compares with the original project cost and timescal…

Answered Asked by Andy Kerr Lab Lodged 29 Jan 2010

The question

To ask the Scottish Executive how the (a) estimated capital value and (b) timescale of the Southern General Hospital compares with the original project cost and timescale estimates.

The answer

Answered by Nicola Sturgeon on 8 Feb 2010 · 10 days after it was lodged, on time

When the new South Glasgow Hospitals and laboratory project was formally announced on 22 May 2008 by Shona Robinson MSP the value of the project was £841.7 million. The value of the scheme remains within £841.7 million.
The February 2008 Outline Business Case (OBC) submitted by NHS Greater Glasgow and Clyde (NHS GG&C) provided indicative construction timescales as these cannot be firmed up until the procurement process is completed and the final building solution and its phasing is known.
The OBC said that the Children''s Hospital would be completed 1st quarter of 2013 and the adult hospital 2nd quarter of 2014. NHS GG&C have indicated that this did not include commissioning time. NHS GG&C have estimated this would have been a maximum period of up to six months. This would have meant the Children''s Hospital being operational 3rd quarter 2013 and adult hospital 4th quarter 2014. Whilst demolitions and landscaping were known to be required the OBC did not set out specifically how and when these would be undertaken.
The procurement process was concluded at the end of 2009 and only then could firmer timescales be stated.
The details of the build programme to be implemented were made available when the preferred bidder was announced on 6 November 2009. The phases are as follows:
Stage 1
- Laboratories construction
Stage 2 “ Final detailed design of the new Children''s and Adult hospitals
Stage 3 “ Construction of the Children''s and Adult''s hospitals
Stage 3a- Demolition of Surgical complex and landscaping.
The successful bidder proposed that both adult and children''s hospitals should be developed concurrently for reasons of operational management, infection control and patient/staff safety.
Both the new adults and children''s hospitals are expected to be completed in January 2015 and fully operational by June 2015. Phase 3a will then be undertaken, whilst both hospitals are operational, and be completed by the summer of 2016.