To ask the Scottish Executive whether it will publish the profile of every infrastructure project of over £10 million.
The answer
The Scottish Government is committed to delivering a tightly managed and sustainable capital programme. We publish details of our proposed capital spending plans in the annual draft budget, provide six-monthly reports to the Public Audit Committee on major capital projects and set out three yearly plans in the Scottish Spending Review. The Infrastructure Investment Plan is published with the express purpose of providing a 10 year perspective on capital projects. The key judgement in assessing the implementation of that programme will be the capital budgets that are available to us.