What the impact will be on the timescale for a decision on the Elgin Flood Alleviation Scheme in light of the reporter’s recent request tha…

Answered Asked by Peter Peacock Lab Lodged 18 Dec 2009

The question

To ask the Scottish Executive what the impact will be on the timescale for a decision on the Elgin Flood Alleviation Scheme in light of the reporter’s recent request that Moray Council provide further details on downstream of Elgin flood risk.

The answer

Answered by Roseanna Cunningham on 12 Jan 2010 · 25 days after it was lodged, on time

It will delay the submission of the report of the inquiry to the Scottish Government. The report of any inquiry must be considered before ministers come to a decision about confirmation of a scheme. At this stage, it is not possible to estimate a timescale as this will depend on a number of factors, not least when the council can provide the information requested, the content thereof and the extent of any further representations by the parties concerned.

In the Official Report

No contribution in the Official Report cites S3W-30228 by reference.