Whether it will provide the (a) terms, (b) cost and (c) cost overrun of the Norland Managed Services contract in each of the last five year…

Answered Asked by George Foulkes Lab Lodged 4 Dec 2009

The question

To ask the Scottish Parliamentary Corporate Body whether it will provide the (a) terms, (b) cost and (c) cost overrun of the Norland Managed Services contract in each of the last five years.

The answer

Answered by Alex Johnstone on 15 Dec 2009 · 11 days after it was lodged, on time

The terms of the Norland Managed Services contract will be provided on request to Procurement Services.
The cost of the Norland Managed Services contract is published on the Parliament''s website and updated quarterly.
Detailed below is the yearly breakdown of expenditure under this contract since contract commencement in July 2004.
Year
| Cost (exc. VAT)

July 2004 “ June2005
| £427,176

July 2005 “ June 2006
| £596,986

July 2006 “ June 2007
| £845,113

July 2007 “ June 2008
| £1,500,693

July 2008 “ June 2009
| £2,625,994

Total Expenditure to June2009
| £5,995,962


The annual contract costs include spend against planned and reactive maintenance and project work.
The total expenditure exceeds the initial estimated contract value of £1.1 million.
Holyrood is a unique building, bespoke in its design, and as the building ages this has an impact on both planned and reactive maintenance. We constantly review and develop our maintenance plans to ensure asset performance meets business needs and cost-effective solutions are delivered.