Further to the answer to question S3W-27550 by Jim Mather on 30 September 2009, whether it will list the (a) name of the project, (b) date …

Answered Asked by Lewis Macdonald Lab Lodged 5 Oct 2009

The question

To ask the Scottish Executive, further to the answer to question S3W-27550 by Jim Mather on 30 September 2009, whether it will list the (a) name of the project, (b) date of application and (c) mega watt capacity of the three applications for extensions to existing wind energy developments that the Scottish Ministers have not yet determined.

The answer

Answered by Jim Mather on 26 Oct 2009 · 21 days after it was lodged, on time

The details of the three applications referred to above are:
1. Black Law wind farm extension
Received “ 25 January 2008
Capacity “ 90MW
| 2. Rothes wind farm extension
Received “ 27 December 2007
Capacity “ 37MW

3. Whitelee wind farm extension Phase II
Received “ 30 May 2009
Capacity “ 162MW