Written Question · S3W-28032 · Session 3

Further to the answer to question S3W-27550 by Jim Mather on 30 September 2009, whether it will list the (a) name of the project, (b) date …

Answered Asked by Lewis Macdonald Lab Lodged 5 Oct 2009

The question

To ask the Scottish Executive, further to the answer to question S3W-27550 by Jim Mather on 30 September 2009, whether it will list the (a) name of the project, (b) date of application, (c) date of consent and (d) mega watt capacity of the extension for the four applications for extensions to existing wind energy developments that the Scottish Ministers have determined.

The answer

Answered by Jim Mather on 26 Oct 2009 · 21 days after it was lodged, on time

The details of the four applications referred to above are:
1. Crystal Rig wind farm Phase II
Received “ 13 June 2007
Consented “ 29 July 2008
Capacity
- 27MW
| 2. Kilbraur wind farm extension
Received “ 13 March 2009
Consented “ 14 September 2009
Capacity
- 20MW

3. Millennium wind farm extension
Received “ 6 January 2009
Consented “ 7 August 2009
Capacity “ 15MW
| 4. Whitelee wind farm extension
Received “ 23 April 2008
Consented “ 20 May 2009
Capacity “ 130MW