Written Question · S3W-27763 · Session 3
Further to the answer to question S3F-1909 by Alex Salmond on 24 September 2009 (Official Report, c. 19971), whether it will itemise the wo…
The question
To ask the Scottish Executive, further to the answer to question S3F-1909 by Alex Salmond on 24 September 2009 (Official Report, c. 19971), whether it will itemise the works or other forms of expenditure that amount to £70 million, showing the costs ascribed to each item and the financial year in which it had been anticipated that this expenditure would have fallen.
The answer
The most recent costs (September 2009) for reprovision/compensation within the Glasgow Airport campus total £70 million (Q3/2013 prices), which is broken down by element in the following table:
Element
| Rounded Value
(£ million)
| Financial Year Spend Would Fall
| Comments
Fuel Farm capital construction costs
| 32
| 2009-10 and 2010-11
| Based on tender returns 2009 from BAA for an enhanced fuel farm
Fuel Farm compensation costs
| 5
| 2010-11
| Based on concluded negotiations involving TS/BAA/Pentland Aviation and the District Valuer
Happitots nursery capital construction costs
| 1.4
| 2009-10 and 2010-11
| Based on construction of new building for BAA to rent to tenant, Happitots at Abbotsinch Rd site
Car Rental Companies back up facilities
| 8
| 2009-10 and 2010-11
| Based on construction of new combined facility to be owned by BAA and operated under various arrangements between BAA and Car Rental Companies at Abbotsinch Rd site
New Multi Storey Car Park (MSCP)
| 11
| 2009-10 and 2010-11
| To reprovide for car rental ready and return area and for affected public car parking spaces. Based on construction of new MSCP to be owned by BAA and operated under various arrangements between BAA and CAR Rental Companies and Car Park operator
BAA compensation claim
| 3.7
| 2012-13
| Based on submission from BAA
Transport Scotland estimated other costs
| 5
| 2010-11 and 2012-13
| Generated by TS and includes estimates for other potentially affected third parties on airport campus and an element of risk provision
Reimbursement of BAA staff and advisor costs
| 3.9
| (£2.6 million) up to 2009-10
(£1.3 million) 2010-11 thru 2012-13
| Costs to develop GARL within the BAA campus under terms of the Master Agreement “ based on invoice values from BAA to da
Element
| Rounded Value
(£ million)
| Financial Year Spend Would Fall
| Comments
Fuel Farm capital construction costs
| 32
| 2009-10 and 2010-11
| Based on tender returns 2009 from BAA for an enhanced fuel farm
Fuel Farm compensation costs
| 5
| 2010-11
| Based on concluded negotiations involving TS/BAA/Pentland Aviation and the District Valuer
Happitots nursery capital construction costs
| 1.4
| 2009-10 and 2010-11
| Based on construction of new building for BAA to rent to tenant, Happitots at Abbotsinch Rd site
Car Rental Companies back up facilities
| 8
| 2009-10 and 2010-11
| Based on construction of new combined facility to be owned by BAA and operated under various arrangements between BAA and Car Rental Companies at Abbotsinch Rd site
New Multi Storey Car Park (MSCP)
| 11
| 2009-10 and 2010-11
| To reprovide for car rental ready and return area and for affected public car parking spaces. Based on construction of new MSCP to be owned by BAA and operated under various arrangements between BAA and CAR Rental Companies and Car Park operator
BAA compensation claim
| 3.7
| 2012-13
| Based on submission from BAA
Transport Scotland estimated other costs
| 5
| 2010-11 and 2012-13
| Generated by TS and includes estimates for other potentially affected third parties on airport campus and an element of risk provision
Reimbursement of BAA staff and advisor costs
| 3.9
| (£2.6 million) up to 2009-10
(£1.3 million) 2010-11 thru 2012-13
| Costs to develop GARL within the BAA campus under terms of the Master Agreement “ based on invoice values from BAA to da