Further to the answer to question S3M-26789 by John Swinney on 8 September 2009, how much of the accelerated capital programme funding for …

Answered Asked by Jeremy Purvis LD Lodged 15 Sep 2009

The question

To ask the Scottish Executive, further to the answer to question S3M-26789 by John Swinney on 8 September 2009, how much of the accelerated capital programme funding for 2009-10 has been spent, in terms of money having been transferred from Scottish Government accounts, also showing where the money has been received and in relation to what projects.

The answer

Answered by John Swinney on 29 Sep 2009 · 14 days after it was lodged, on time

The decision to accelerate spending was taken in order to speed progress on a range of specific projects, and work is continuing to deliver these projects. The associated spending is being committed in accordance with government procurement and accounting procedures, and will be transferred to contractors'' and others'' accounts as invoices are presented. We forecast that all of the accelerated capital will be spent in the course of 2009-10, as planned.

In the Official Report

No contribution in the Official Report cites S3W-27285 by reference.