What Transport Scotland estimates projected daily traffic flow levels will be for the various sections of the new M80 from Stepps to Haggs …
The question
To ask the Scottish Executive what Transport Scotland estimates projected daily traffic flow levels will be for the various sections of the new M80 from Stepps to Haggs in 2020.
The answer
Transport Scotland estimates that the average annual daily traffic flows on the various sections of the new M80 from Stepps to Haggs in 2020 will be approximately:
Hornshill to Mollinsburn “ 56,600 vehicles.
Mollinsburn to Auchenkilns “ 105,100 vehicles.
Auchenkilns to Old Inns “ 89,100 vehicles.
Old Inns to Haggs “ 97,700 vehicles.
Hornshill to Mollinsburn “ 56,600 vehicles.
Mollinsburn to Auchenkilns “ 105,100 vehicles.
Auchenkilns to Old Inns “ 89,100 vehicles.
Old Inns to Haggs “ 97,700 vehicles.