What the estimated cost is of constructing a Rosyth bypass and whether it will provide a breakdown of costs.

Answered Asked by Jim Tolson LD Lodged 14 Jul 2009

The question

To ask the Scottish Executive what the estimated cost is of constructing a Rosyth bypass and whether it will provide a breakdown of costs.

The answer

Answered by Stewart Stevenson on 6 Aug 2009 · 23 days after it was lodged, on time

A Rosyth bypass has not been identified as a national strategic priority and consequently no studies have been carried out by Transport Scotland to examine the feasibility or costs associated with a bypass for Rosyth.