Further to the answer to question S3W-23788 by Stewart Stevenson on 20 May 2009, what effect the completion of the UP passenger loop at Sti…

Answered Asked by Dr Richard Simpson Lab Lodged 21 May 2009

The question

To ask the Scottish Executive, further to the answer to question S3W-23788 by Stewart Stevenson on 20 May 2009, what effect the completion of the UP passenger loop at Stirling railway station could or will have on the timings of the Alloa to Glasgow and Edinburgh passenger link and on freight train operations by DB Schenker Freight Trains.

The answer

Answered by Stewart Stevenson on 2 Jun 2009 · 12 days after it was lodged, on time

The creation of a double junction and new UP passenger loop at Stirling railway station will facilitate journey time savings of up to five minutes for a number of Alloa to Glasgow trains. The new facilities will increase the flexibility of the route, assisting in the punctual working of passenger and freight trains offering small, but widespread benefits, across a wide area of central Scotland.