Written Question · S3W-23903 · Session 3
Further to the answers to questions S3W-23196 to S3W-23200 by Stewart Stevenson on 5 May 2009, whether Scottish Water’s capital expenditure…
The question
To ask the Scottish Executive, further to the answers to questions S3W-23196 to S3W-23200 by Stewart Stevenson on 5 May 2009, whether Scottish Water’s capital expenditure programme was overspent against estimate for the year to 31 March 2009 and, if so, what the level was of over expenditure.
The answer
Scottish Water is tasked with delivering a £2.4 billion capital investment programme between 2006-10. In their Delivery Plan update for 2008-09 Scottish Water forecast that they would deliver between £650 million to £690 million of this investment. Their provisional outturn figure is £687 million.