Further to the answer to question S3W-21885 by Stewart Stevenson on 2 April 2009, whether it will set out its timetable for design and cons…
The question
To ask the Scottish Executive, further to the answer to question S3W-21885 by Stewart Stevenson on 2 April 2009, whether it will set out its timetable for design and consultative stages in relation to the upgrading of the A82 and when a comprehensive plan will be available.
The answer
This government is committed to upgrading the A82 on a continuing and progressive basis as a key priority and improvements at Pulpit Rock and a bypass for Crianlarich are already planned within the current programme.
The Strategic Transport Projects Review (STPR) provides a robust framework of prioritised schemes, the delivery of which will be considered in future spending reviews.
A timetable for undertaking work associated with the upgrading of the A82 will be set in the context of overall affordability and our commitments to other STPR proposals.
The Strategic Transport Projects Review (STPR) provides a robust framework of prioritised schemes, the delivery of which will be considered in future spending reviews.
A timetable for undertaking work associated with the upgrading of the A82 will be set in the context of overall affordability and our commitments to other STPR proposals.
In the Official Report
No contribution in the Official Report cites S3W-22639 by reference.