Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S3W-21939 · Session 3

Further to the answer to question S3W-21604 by Kenny MacAskill on 10 March 2009, what progress has been made to select and acquire a suitab…

Answered Asked by Mary Scanlon Con Lodged 13 Mar 2009

The question

To ask the Scottish Executive, further to the answer to question S3W-21604 by Kenny MacAskill on 10 March 2009, what progress has been made to select and acquire a suitable site for HMP Highland.

The answer

Answered by Kenny MacAskill on 19 Mar 2009 · 6 days after it was lodged, on time

I have asked Mike Ewart, Chief Executive of the Scottish Prison Service to respond. His response is as follows:
The Scottish Prison Service, working in conjunction with Highland Council, has identified possible sites for the proposed HMP Highland and further work is now being carried out to evaluate the suitability of these sites. This work is in progress.

In the Official Report

No contribution in the Official Report cites S3W-21939 by reference.