Further to the answers to questions S3W-11032 and S3W-11033 by Michael Russell on 16 April 2008, whether it considers that the Scottish Env…

Answered Asked by Des McNulty Lab Lodged 9 Mar 2009

The question

To ask the Scottish Executive, further to the answers to questions S3W-11032 and S3W-11033 by Michael Russell on 16 April 2008, whether it considers that the Scottish Environment Protection Agency’s (SEPA) decision to approve the Aviemore resort hotels master plan without a satisfactory flood risk assessment on 4 December 2007 complied with its requirement to adhere to statutory guidance on sustainable development and ensure that its actions enforced high environmental standards and, if so, what the reasons are for the Scottish Government’s position on this matter; which part of the guidance it considers SEPA to have complied with, and in what other instances SEPA or it has supported such an action as sustainable.

The answer

Answered by Roseanna Cunningham on 19 Mar 2009 · 10 days after it was lodged, on time

The decision by SEPA to withdraw its objection to the master plan on 4 December 2007 was an operational matter for SEPA. I understand that SEPA is satisfied that the decision was appropriate in the circumstances of the case, and ensured that the environment and human health were adequately protected. SEPA''s approach was entirely consistent with section 3 of the statutory guidance given to the agency on sustainable development.

In the Official Report

No contribution in the Official Report cites S3W-21696 by reference.