Written Question · S3W-21135 · Session 3
Further to the answer to question S2W-29564 by Malcolm Chisholm on 4 December 2006, whether actual costings are now available and, if so, w…
The question
To ask the Scottish Executive, further to the answer to question S2W-29564 by Malcolm Chisholm on 4 December 2006, whether actual costings are now available and, if so, what these are.
The answer
The Homelessness etc (Scotland) Act 2003 is still in the process of being implemented. In any event, robust information on the costs of implementation is not held centrally as it is for each local authority and their partners to allocate resources for this purpose on the basis of local needs and priorities. It is not possible to accurately disaggregate costs which assist in preventing and tackling homelessness, whether specifically for the purposes of implementing this legislation or otherwise, across the wide range of bodies and activities this will encompass.
In the Official Report
No contribution in the Official Report cites S3W-21135 by reference.