Written Question · S3W-21036 · Session 3
On what date Scottish ministers took the decision that the Strategic Transport Projects Review should be extended to cover the additional d…
The question
To ask the Scottish Executive on what date Scottish ministers took the decision that the Strategic Transport Projects Review should be extended to cover the additional decade between 2022 and 2032.
The answer
The scale and phased implementation of a number of the 29 recommended schemes contained within the STPR means they may take longer to complete than the 10 years between 2012 and 2022.
In the Official Report
No contribution in the Official Report cites S3W-21036 by reference.