Written Question · S3W-19420 · Session 3
What budget has been allocated to the proposed upgrading of the Dalry bypass.
The question
To ask the Scottish Executive what budget has been allocated to the proposed upgrading of the Dalry bypass.
The answer
The Strategic Transport Projects Review (STPR) has recommended 29 nationally strategic transport schemes over the next 20 years that will let us plan for the delivery of an efficient, integrated transport network fit for the 21st century.
Project 22 within the STPR is a nationwide project targeting road congestion and environmental impact factors, surrounding specific locations around the trunk road network including the A77, A720, A96 and the A737.
One of the examples within this project is a bypass on the A737 at Dalry and the Scottish ministers, through Transport Scotland, will develop this and other suitable schemes as resources and the STPR''s wider priorities allow.
The STPR is not a funding document however the cost estimate for the delivery of the package of measures within Project 22 is £100 to £250 million.
Project 22 within the STPR is a nationwide project targeting road congestion and environmental impact factors, surrounding specific locations around the trunk road network including the A77, A720, A96 and the A737.
One of the examples within this project is a bypass on the A737 at Dalry and the Scottish ministers, through Transport Scotland, will develop this and other suitable schemes as resources and the STPR''s wider priorities allow.
The STPR is not a funding document however the cost estimate for the delivery of the package of measures within Project 22 is £100 to £250 million.