Written Question · S3W-18663 · Session 3
Whether agreement has been reached regarding the financial contribution to the cost of the planned replacement of the main expansion joints…
The question
To ask the Scottish Executive whether agreement has been reached regarding the financial contribution to the cost of the planned replacement of the main expansion joints of the Forth Road Bridge; whether a preferred bidder has been appointed; when the works will be carried out; what the Scottish Government’s contribution will be, and what the projected cost is.
The answer
Following the announcement on 10 December about our future strategy for the Forth crossing, we will be exploring with the Forth Estuary Transport Authority options for the timing, costs and extent of the works to replace the expansion joints.
In the Official Report
No contribution in the Official Report cites S3W-18663 by reference.