Written Question · S3W-18289 · Session 3
Further to the answer to question S3W-16790 by Stewart Maxwell on 28 October 2008, how many (a) off-the-shelf units and (b) land acquisitio…
The question
To ask the Scottish Executive, further to the answer to question S3W-16790 by Stewart Maxwell on 28 October 2008, how many (a) off-the-shelf units and (b) land acquisitions are currently being progressed.
The answer
The Cabinet Secretary for Health and Wellbeing announced a second tranche of the accelerated £30 million programme for 2008-09 on 28 November 2008. From both tranches announced to date there are 28 units (three projects) of off-the-shelf units being progressed and 16 sites with the capacity for 475 units are being progressed for acquisition. There are also 538 units of accelerated construction being progressed. A further announcement is still to be made on the remaining funding available for 2008-09.