Written Question · S3W-17424 · Session 3
Further to the answer to question S3W-16452 by Stewart Maxwell on 26 September 2008, what work has now been carried out in relation to the …
The question
To ask the Scottish Executive, further to the answer to question S3W-16452 by Stewart Maxwell on 26 September 2008, what work has now been carried out in relation to the amount being brought forward in the Affordable Housing Investment Programme from 2010-11 and what the consequent impact will be on planned units and investment for affordable housing in each local authority in 2008-09.
The answer
Much progress has been achieved since September.
On 7 October we announced the first £9 million tranche of this accelerated funding which will assist the acceleration of construction activity and the purchase of sites as follows:
Accelerated Construction Activity
LA Area
| No. of Projects
| 2008-09
Est. Spend
| Est. Units
| Tenure
Moray
| 2
| £1.441 million
| 36
| RSL Rent
Argyll and Bute
| 1
| £0.450 million
| 10
| RSL Rent
Dumfries and Galloway
| 1
| £1.000 million
| 310
| RSL Rent
Scottish Borders
| 1
| £0.660 million
| 33
| 25 RSL Rent
8 LCHO
Fife
| 1
| £0.500 million
| 22
| 16 Rent
6 LCHO
Total
| 6
| £4.051 million
| 411
| 395 RSL Rent
16 LCHO
Site Acquisitions
LA Area
| No. of Projects
| 2008-09
Est. Spend
| Est. Units
| Tenure
Highland
| 5
| £1.880 million
| 98
| To be confirmed
On 7 October we announced the first £9 million tranche of this accelerated funding which will assist the acceleration of construction activity and the purchase of sites as follows:
Accelerated Construction Activity
LA Area
| No. of Projects
| 2008-09
Est. Spend
| Est. Units
| Tenure
Moray
| 2
| £1.441 million
| 36
| RSL Rent
Argyll and Bute
| 1
| £0.450 million
| 10
| RSL Rent
Dumfries and Galloway
| 1
| £1.000 million
| 310
| RSL Rent
Scottish Borders
| 1
| £0.660 million
| 33
| 25 RSL Rent
8 LCHO
Fife
| 1
| £0.500 million
| 22
| 16 Rent
6 LCHO
Total
| 6
| £4.051 million
| 411
| 395 RSL Rent
16 LCHO
Site Acquisitions
LA Area
| No. of Projects
| 2008-09
Est. Spend
| Est. Units
| Tenure
Highland
| 5
| £1.880 million
| 98
| To be confirmed
In the Official Report