Further to the First Minister’s statement on 24 September 2008 that “£1 billion of new private sector investment in the renewable energy se…
The question
To ask the Scottish Executive, further to the First Minister’s statement on 24 September 2008 that “£1 billion of new private sector investment in the renewable energy sector” had “been made in the past two months alone” (Official Report, c.11088), whether it will list the projects in question, also showing the value of each and the date on which the relevant investment decision was made.
The answer
The projects in question, and the associated levels of investment, where this is already in the public domain, are as follows;
Clyde windfarm, £600 million;
Biomass plant at the Tullis Russell paper mill in Markinch, commercial in confidence;
Extension to Crystal Rig windfarm, £22 million;
Glendoe Hydro scheme, over £140 million.
The statement highlighted some of the many renewable energy projects which reached various stages in their development over the course of the summer, demonstrating the high level of activity underway across the sector in Scotland.
The dates on which the relevant investment decisions were made are a matter for the private companies concerned.
Clyde windfarm, £600 million;
Biomass plant at the Tullis Russell paper mill in Markinch, commercial in confidence;
Extension to Crystal Rig windfarm, £22 million;
Glendoe Hydro scheme, over £140 million.
The statement highlighted some of the many renewable energy projects which reached various stages in their development over the course of the summer, demonstrating the high level of activity underway across the sector in Scotland.
The dates on which the relevant investment decisions were made are a matter for the private companies concerned.
In the Official Report