Written Question · S3W-16476 · Session 3
Further to the answer to question S3O-4193 by Stewart Stevenson on 18 September 2008, when it expects the feasibility study looking at the …
The question
To ask the Scottish Executive, further to the answer to question S3O-4193 by Stewart Stevenson on 18 September 2008, when it expects the feasibility study looking at the provision of traffic signals at Cadham junction to be completed.
The answer
I expect the traffic signal feasibility study at Cadham to be finalised by the end of October 2008.
In the Official Report
No contribution in the Official Report cites S3W-16476 by reference.