Written Question · S3W-16443 · Session 3
Further to the answer to question S3W-15802 by Nicola Sturgeon on 17 September 2008, how many of the 73 staff from the Vale of Leven Hospit…
The question
To ask the Scottish Executive, further to the answer to question S3W-15802 by Nicola Sturgeon on 17 September 2008, how many of the 73 staff from the Vale of Leven Hospital who registered for cleanliness champion training have received that training and when.
The answer
I am advised by NHS Greater Glasgow and Clyde that of the 73 staff who registered since May 2007 for the cleanliness champions programme, a total of 23 have now completed it. It is not possible to specify precisely when each member of staff completed their training as this will depend on when the staff member enrolled, but the programme takes approximately 20 hours to complete.