Whether it will confirm that the funding allocated to registered social landlords for 2008-09 is £85 million less than was allocated for 20…
The question
To ask the Scottish Executive whether it will confirm that the funding allocated to registered social landlords for 2008-09 is £85 million less than was allocated for 2007-08.
The answer
The amount of Housing Investment varies across Scotland from year-to-year depending on a number of circumstances including land availability, opportunities to meet identified need and carry-forward commitments from previous years. The initial allocation to Registered Social Landlords (RSLs) for 2008-09 is £64 million less than was allocated in 2007-08. This reflects the tighter overall spending settlement for the Scottish Government in 2008-09. Over £1.5 billion of funding will be made available through the Affordable Housing Investment Programme over the three years
2008-09 to 2010-11. Funding in 2008-09 and 2009-10 will be augmented by the accelerated funding of up to £100 million announced on 19 August 2008 as part of the Scottish Government''s paper Responding to the Changing Economic Climate: Further Action on Housing. The resources allocated to RSLs will substantially increase in 2009-10 due to both planned increased spend profiles and the accelerated funding announced on 19 August.
2008-09 to 2010-11. Funding in 2008-09 and 2009-10 will be augmented by the accelerated funding of up to £100 million announced on 19 August 2008 as part of the Scottish Government''s paper Responding to the Changing Economic Climate: Further Action on Housing. The resources allocated to RSLs will substantially increase in 2009-10 due to both planned increased spend profiles and the accelerated funding announced on 19 August.
In the Official Report