Written Question · S3W-15188 · Session 3
Further to the answer to question S3W-14775 by Stewart Stevenson on 23 July 2008, how much additional funding to cover the increase in fuel…
The question
To ask the Scottish Executive, further to the answer to question S3W-14775 by Stewart Stevenson on 23 July 2008, how much additional funding to cover the increase in fuel costs has been given to NorthLink Ferries Ltd and CalMac Ferries Ltd since the signing of the relevant public service contracts.
The answer
We have paid additional fuel supplements totalling £2.5 million to NorthLink Ferries Ltd since the Northern Isles contract started in July 2006 and £3.4 million to CalMac Ferries Ltd since the Clyde and Hebrides contract started in October 2007.
In the Official Report
No contribution in the Official Report cites S3W-15188 by reference.