Parliament Workbench
Data: Motions & questions to 19 Nov 2026

Written Question · S3W-14581 · Session 3

Further to the answer to question S3W-13758 by Stewart Maxwell on 10 June 2008, exactly what criteria were used to make an assessment of th…

Answered Asked by Bill Butler Lab Lodged 24 Jun 2008

The question

To ask the Scottish Executive, further to the answer to question S3W-13758 by Stewart Maxwell on 10 June 2008, exactly what criteria were used to make an assessment of the most effective way to continue value for money delivery of its central heating programme.

The answer

Answered by Stewart Maxwell on 3 Jul 2008 · 9 days after it was lodged, on time

The criteria used to decide on an extension to the contract for delivery of the central heating programme included the timing, risks and costs involved. As the future shape of the programme cannot be determined while the review is underway, it was decided not to initiate a full tender process until this is clear.

In the Official Report

No contribution in the Official Report cites S3W-14581 by reference.