The question
To ask the Scottish Executive, further to the answers to questions S3W-11249 and S3W-12807 by Michael Russell on 22 April and 21 May 2007 respectively, on what precise date officials became aware of a potential conflict of interest between developers seeking to attract the same supermarket to rival proposals for retail developments in Aviemore.
The answer
Scottish Government officials only became aware of a potential conflict subsequent to the Cairngorms National Park Authority granting planning permission on 11 January 2008. Attention was specifically drawn to the issue of conflict in correspondence from the developer dated 5 February 2008.