Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S3W-13652 · Session 3

Further to the answer to question S3W-12868 by Stewart Stevenson on 29 May 2008, when the contracts for (a) Ernst and Young LLP and (b) Bro…

Answered Asked by Des McNulty Lab Lodged 29 May 2008

The question

To ask the Scottish Executive, further to the answer to question S3W-12868 by Stewart Stevenson on 29 May 2008, when the contracts for (a) Ernst and Young LLP and (b) Brodies LLP were awarded; what the specification of the work required was in each instance, and whether the consultants reports will be made available in the Scottish Parliamentary Information Centre.

The answer

Answered by Stewart Stevenson on 1 Jul 2008 · 33 days after it was lodged, 19 days after it was due

Ernst and Young LLP were engaged in October 2006 with a remit for financial elements including revenues and growth, fares and affordability, and options on the Scotrail franchise extension.
Brodies LLP were engaged in January of 2007 with a remit to consider legal, including contractual and procurement, issues around the franchise extension.
Additional material including work by both Ernst and Young and Brodies will be made available in the Scottish Parliament Information Centre and the Transport Scotland website.

In the Official Report

No contribution in the Official Report cites S3W-13652 by reference.