Parliament Workbench
Data: Motions & questions to 19 Nov 2026

Written Question · S3W-12806 · Session 3

How many PPP/PFI projects since 3 May 2007 have (a) been submitted to the Scottish Government for approval, and (b) received approval.

Answered Asked by Elaine Murray Lab Lodged 8 May 2008

The question

To ask the Scottish Executive how many PPP/PFI projects since 3 May 2007 have (a) been submitted to the Scottish Government for approval, and (b) received approval.

The answer

Answered by John Swinney on 16 May 2008 · 8 days after it was lodged, on time

The standard form of PFI developed across the UK has not been used in Scotland for any projects which have commenced from 3 May 2007 onwards. We said before the elections that PPP could continue as one of several delivery options open to public sector bodies. Our preference is for the Non Profit Distributing (NPD) model to be used.
For those PFI projects which were well advanced, it did not make sense to unpick these deals as this would have come at a high cost
- not just money but delays in new facilities for the public. There have been ten PFI projects which fall into this category and which have received approval since last May.

In the Official Report

2 contributions mention S3W-12806
  1. 27 May 2008
    Methods of Funding Capital Investment Projects Inquiry
    Elaine Murray Lab Finance Committee

    I have many questions about the Scottish futures trust, but I will start by asking about the difference between PPP and the non-profit-distributing model that the Government favours. I will refer to evidence that has been given to the comm…

  2. 27 May 2008
    Methods of Funding Capital Investment Projects Inquiry
    Elaine Murray Lab Finance Committee

    I have a point of information. In the cabinet secretary's answer to my parliamentary question S3W-12806, he described the 10 schools that have been funded under the NPD model as PFI projects.