The question

To ask the Scottish Executive, further to the answer to question S3W-12231 by Stewart Stevenson on 7 May 2008, whether this answer indicates that it still intends to build the Aberdeen Western Peripheral Route using the PPP/NPD funding method.

The answer

Answered by Stewart Stevenson on 22 May 2008 · 14 days after it was lodged, on time

As set out in the Infrastructure Investment Plan 2008, the Aberdeen Western Peripheral Route will be considered for procurement through the non-profit distributing model.