What steps it will take to secure an increase in the carrying capacity of the undersea electricity cable from Carradale in Kintyre to Imach…

Answered Asked by Kenneth Gibson SNP Lodged 17 Mar 2008

The question

To ask the Scottish Executive what steps it will take to secure an increase in the carrying capacity of the undersea electricity cable from Carradale in Kintyre to Imachar in Arran.

The answer

Answered by Jim Mather on 16 Apr 2008 · 30 days after it was lodged, on time

Management of the Transmission Network in this area is primarily a matter for Scottish and Southern Energy and National Grid. We understand that there is interest in increased generation opportunities in the area, although the current system only provides limited potential for exporting electricity. Scottish and Southern Energy are currently reviewing transmission solutions to try to release additional capacity on this network. The Scottish Government is in contact with Scottish and Southern Energy on this issue and will meet National Grid very shortly.