Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S3W-10691 · Session 3

Further to the answer to question S3W-9289 by Stewart Stevenson on 21 February 2008, what the reasons are for the continuing delay to the c…

Answered Asked by George Foulkes Lab Lodged 4 Mar 2008

The question

To ask the Scottish Executive, further to the answer to question S3W-9289 by Stewart Stevenson on 21 February 2008, what the reasons are for the continuing delay to the completion of the West Edinburgh Planning Framework.

The answer

Answered by Stewart Stevenson on 13 Mar 2008 · 9 days after it was lodged, on time

Further to my answer to question S3W-9289 regarding preparation of the West Edinburgh Planning Framework, issues regarding transport components have been particularly complex. However, officials are now in agreement as to a way forward and the document will proceed to finalisation as soon as possible.

In the Official Report

No contribution in the Official Report cites S3W-10691 by reference.