Written Question · S3W-08423 · Session 3
What costs were provided by CalMac Ferries Ltd for the operation of options that it presented to achieve the introduction of a ferry servic…
The question
To ask the Scottish Executive what costs were provided by CalMac Ferries Ltd for the operation of options that it presented to achieve the introduction of a ferry service from Lochboisdale to Mallaig at the time of the tendering exercise for current services, or since.
The answer
The mandatory “variant bid”for a dedicated service between Mallaig and Lochboisdale required the purchaseof an additional vessel with a suggested capital cost of £25 million andadditional running costs of £4 million per annum.
The “optional variant bid”would have required significant changes to services to Barra and an additionalsubsidy of some £600,000 per annum.
The “optional variant bid”would have required significant changes to services to Barra and an additionalsubsidy of some £600,000 per annum.
In the Official Report